Give & Go

Silo Pads

https://www.lakdhillon.com/wp-content/uploads/2024/02/20231224_100559.jpg
https://www.lakdhillon.com/wp-content/uploads/2024/02/20231224_100551.jpg
https://www.lakdhillon.com/wp-content/uploads/2024/02/2-8.jpg
https://www.lakdhillon.com/wp-content/uploads/2024/02/1-8.jpg
https://www.lakdhillon.com/wp-content/uploads/2024/02/3-4.jpg
https://www.lakdhillon.com/wp-content/uploads/2024/02/4-6.jpg
https://www.lakdhillon.com/wp-content/uploads/2024/02/5-4.jpg
https://www.lakdhillon.com/wp-content/uploads/2024/02/20231224_095734.jpg
https://www.lakdhillon.com/wp-content/uploads/2024/02/20231224_095157.jpg
https://www.lakdhillon.com/wp-content/uploads/2024/02/20231220_141725.jpg
https://www.lakdhillon.com/wp-content/uploads/2024/02/6-4.jpg
https://www.lakdhillon.com/wp-content/uploads/2024/02/20221218_092318.jpg
https://www.lakdhillon.com/wp-content/uploads/2024/02/20231218_150449.jpg
https://www.lakdhillon.com/wp-content/uploads/2024/02/20231218_164030.jpg

Project: Give & Go

Title:

Description:

Give & Go

Silo Pads


Business Objective

Build a foundation to support four 5-story 15,000 kg silos and tractor trailer pads.

The client had an accelerated schedule for construction due to year-end budgetary spend. A six-week project was therefore delivered in three weeks despite bad weather conditions. The metal plates within the foundation on which the silo base will be welded needed to be precise to ensure structural continuity to support 15,000kg of wheat and sugar.

 


20231224_100559
20231224_100551
2
1
3
4
5
20231224_095734
20231224_095157
20231220_141725
6
20221218_092318
20231218_150449
20231218_164030


About

logo-lak-dhillon

We build things because we like to...